Construction schedule

  • Erection of the steel structure: start on Monday, July 15, 2024
  • Electrical work: planned for the 28th and 29th calendar week, i.e. from July 8, 2024
  • Dismantling of the old book transport system: from July 22 to August 16, 2024, rescheduled from August 21 - 23, 2024
  • Construction of the new counter: from August 12 to August 16, 2024, rescheduled from 9 - 13.9.2024, new from 18.11.24
  • Dismantling of the previous service point: planned for the week from August 26 to August 30, 2024, during which time the flooring will also be renewed and the new counter area will be enhanced with a "point cloud", similar to the points on the windows, delayed
  • Commissioning of the new counter: planned for August 26, 2024, rescheduled from September 16, 2024

During this period, we will endeavor to maintain library services as continuously as possible. Thank you for your understanding during this phase of the library's development at the Central Campus and we look forward to presenting you with a modernized and improved service area soon. If you have any questions or comments, please do not hesitate to contact us

©Architekturbüro mayerwittig